機關地址
No.70, Mizhi, Nanxi Dist., Tainan City 71544, Taiwan (R.O.C.)
是否屬二以上機關之聯合採購(不適用共同供應契約規定)
否
原公告日期
105/03/30 原公告日期係指最近1次招標公告或更正日期
傳輸已簽准之內容檔案名稱
預期使用情形及其效益目標簽.pdf
履約地點(含地區)
嘉義縣-大埔,高雄市-桃源區,高雄市-那瑪夏區
廠商名稱
SINOTECH ENGINEERING CONSULTANTS, LTD.
廠商名稱(英)
SINOTECH ENGINEERING CONSULTANTS, LTD.
廠商地址
14th Floor, 171, Nanking E. Road, Sec. 5, Taipei 105, Taiwan
廠商地址(英)
14th Floor, 171, Nanking E. Road, Sec. 5, Taipei 105, Taiwan
得標廠商國別
中華民國(Republic of China (Taiwan))
履約起迄日期
105/04/28 - 108/12/31 (預估)
品項名稱
「曾文水庫越域引水工程計畫-流域環境監測與變動趨勢評估」
原產地國別1
中華民國(Republic of China (Taiwan))
評選委員
出席會議 姓名 職業
否 林鎮洋 國立臺北科技大學教授
否 丁澈士 國立屏東科技大學土木工程系教授
是 周乃昉 國立成功大學水利及海洋工程學系教授
是 吳正逵 已退休
是 蔡義發 已退休
否 賴伯勳 已退休
是 林美香 正工程司兼課長
是 何達夫 正工程司兼課長
否 莫評任 簡任正工程司
是 陳人敬 簡任正工程司
是 連上堯 副局長
附加說明
This project is continuing to monitor the watershed of Zengwen Reservoir Transbasin Diversion project sites, and evaluates the environmental variations and trends (e.g. bare land area and/or riverbed development) based on the monitoring data. In addition, risk-index of new water intake works under this sediment environment is also established and evaluated in this project. According to the evaluation of risk-index, possible plans of new water intake works are proposed. Also, future direction of Zengwen Reservoir Transbasin Diversion Project will be proposed by taking into consideration Zengwen Reservoir storage capacity as well as water supply and demand of southern area.
The working items of this project include:
1. Environmental monitoring of Laonong and Qishan River basin
(1) Compilation of fundamental watershed data
(2) Monitoring and analysis for landslides and debris flow
(3) Monitoring of discharge and suspended-sediment concentrations, and analysis of streambed evolution
(4) Risk-index establishment and evaluation for new water intake works
2. Evaluation for possible plans of new water intake works
(1) Possible plans of new intake works at Laonong River
(2) Possible plans of new intake works at Qishan River
3. Function review of Zengwen Reservoir Transbasin Diversion project including sedimentation analysis of Zengwen Reservoir and review of water supply and demand of southern area
4. Other appurtenant work
It is noted that the formal award of contract will be conducted only after the amendment of "Zengwen Reservoir Transbasin Diversion Project-Typhoon Morakot Post-processing Program" has been officially approved by the Executive Yuan. For more details please refer to the tender documentation.